This article applies to:
- Enterprise Reporter
- Product 2.x
Question:
- How do I schedule a saved report to run?
Reply:
Once a report view has been saved, it can be scheduled to run at a designated time.
To schedule a report to run:
1. Go to the Settings menu in the navigation panel and select Event Schedule.
2. In the Event Schedules window, click Add Event.
3. In the Add Event to Schedule pop-up box, select the Report to Run from the saved custom reports listed in the pull-down menu.
4. Specify criteria for scheduling the event, and then click Save
Notes: